541.225.000 adet/yıl KIRŞEHİR/TÜRKİYE
Steel structure
High/low pressure process piping fabrication and installation
Equipment installation lnstrumentation
3 x 38.5 tons/hoursteam capacity
Boilerfabrication and installation
Precommissioning , commissioning
and start-up
Ope ration, maintenance and repairworks forthree years with more than 500 personnel
Tyre wagons fabrication and installation

TECEN / TÜRKMENİSTAN

Ammonia: 600 tons/dayUrea: 1050 tons/day Ammonia Complex: 13 Units
Urea Complex: 8 Units Auxiliary System :12 Units Steam Boiler : 145 Vh
Power Generator: 2x18,75 MVA Mechanical Erection Works:
• Synthesis and Production Units
• Boiler
• Reformer
• Turbine& Compressors
• High/LowPressure Piping
• Water Treatment System
• Auxiliary Units
• Refractory &Rubber Lining
• Stacker &Reclaimer
• Steel Construction

RAFİNERİ VE PETROKİMYA TESİSLERİ
TÜPRAŞ Kırıkkale Rafinerisi
TECEN Amonyak ve Üre Tesisi
Petlas Lastik Fabrikası
TÜPRAŞ Aliağa Rafinerisi
TÜPRAŞ İzmit Rafinerisi
İran Arak Rafinerisi
KIRIKKALE / TURKEY
The design, supply, construction and erection services of project have been fulfilled on turnkey lump sum basis by consortium of TEKNOTES and SOFRESID S.A./France. The Provisional Acceptance of the project has been attained in 1997 and the Final Provisional Acceptance in1999. in addition to the complete detailed design and partial basic engin nering, all construction and erection services, alsa the supply of steel structure, static equipments (Heat exchangers,Drums , Adsorbers , Columns ete.), electrical equipment and materials ete. have been carried aut by TEKNOTES. At the piant, the low Octane Number Naphtha is used as raw material and unleaded gasoline is produced as end product.

TÜPRAŞ KIRIKKALE RAFİNERİSİ HYDROCKER TESİSİ
Yüksek / alçak basınç proses borulama imalatı ve montajı
Çelik konstrüksiyon imalatı ve montajı
İnşaat işleri Döner ekipman montajı
Elektrik ve enstrümantasyon Refakat hatları imalatı ve montajı
Ex-Proof Tavan Vinci imalat ve montajı
Ekipman Montajı
Rewamp ünitesi imalatı ve montajı
Detay mühendislik

2x330/GALABOVO / BULGARIA


2 x 150 MW KANGAL / SIVAS / TURKEY
Boiler erection
High/low pressure proses piping fabrication and installation
Off-site piping fabrication and installation
Civil works
Rotary equipment erection
Electrical works and instrumentation
Equipment installation
Fabrications and installations in the machine hail
Fabrication, supply and installation of mud scrappers tor raw water intake pools

9 x 150 MW AMBARLI / ISTANBUL / TURKEY

Mechanical Works
Electrical
lnstrumentation and comtrol
High/low pressure proses piping fabrication and installation
Steel structure fabrication and installation

2*160 MW ÇAYIRHAN / ANKARA / TÜRKİYE


5x120 MW/RABIGH / Saudi Arabia


2 x 150 MW ZONGULDAK / TURKEY
Boiler erection
High/low pressure proses piping fabrication and installation
Off-site piping fabrication and installation
Steel structure fabrication and installation
Electrofilters and dust precipitators fabrication and installation
Civil works
Rotary equipment erection
Electrical works and instrumentation
Equipment installation
Fabrications and installations in the machine hail
Fabrication, supply and installation of mud scrappers tor raw water intake pools
CATALAGZI THERMAL POWER PLANT SLUDGE DEWATERING AND COAL MIXING-WASHERY PLANT WITH LONG DISTANCE BELT CONVEYOR
363560 m, 400 tons/h CATALAGZI/ ZONGULDAK / TURKEY
Length 3560 m
3560 m, 400 tons/hour
Steel structure fabrication and installation
Rotary equipment erection
lnstrumentation
Medium-Tensile and Low-Tensile (MV/LV)electrical installation works
Equipment erection
Commissioning

1 x 210 MW-BURSA-TURKEY
1 x 21O MW Orhaneli Thermal Power Plant Flue Oesulphurization Plant was constructed by the consortium TEKNOTES and NOELL - KRC / Germany and put into operation on 21.11.1997.The limestone wet scrubbing process retrofitted to the Orhaneli Power Plant is the most common commercial process in the world for a like power plants. A limestone powder water slurry is the scrubbing medium and gypsium slurry is the end product. The plant has SO, removal efficiency of 95%. TEKNOTES SO, has implemented all detail engineering, civil works, ıocal material supply, mechanical and equipment erection, process piping, raw water treatment plant, electrical material supply and installation, instrumentation and commissioning activities forthis plant.
PROCESS SCHEME


ORHANELİ TERMİK SANTRALİ KÖMÜR PARK MAKİNESİ MONTAJI VE İŞLETMEYE ALINMASI
770 tons/hour BURSA / TÜRKİYE


This project is included in the investment program in 1996 in order to use the 70,000,000 tons highsulphur lignite coal reserve located 1996 near Can for power generation purposes and to meet the ever-increasing domestic demand for energy.
STEAM GENERATOR
|
|
STEAM TURBINE
|
Manufacturer: ALSTOM POWER
|
GENERATOR
|
Manufacturer: ALSTOM POWER |
BOILER PROCESS SCHEME |
![]() |
SCOPE OF TEKNOTES
Projeci Managementfor its part
Construction Management
Basic and Detail Engineering
Procurement
Manufacturing of Steel Structure
Manufacturing of Ducting System
Commissioning
AII civil construclion activities
Excavation and backfilling fora total of 2.500.000 cubic meters Substructure and superstructure works fora total of 70.000 cubic meters concrete foundations
Asphalt pavement access roads fora total of 2500 cubic meters lnternal concrete road and pavementfor atotal of 37.000 sq. meters Reinforced Concrete bridge lenghtfor atotal of 50 meters
4 pieces of limestone silos, each capacity 6000 cubic meters (sliding forework system, silo diameter 14 meters, height 36 meters)
Ash disposal area 200.000 cubic meters filing embankment 8 pieces logistics bulding (non-technical buildings)
9000 sq. meters total closed area of buildings
6000 meters service road and open drainage channel
500 meters bored piles diameter 80 centimeters, lenght 12 meters
2 pieces chimney (corten steel) diameter 4,5 meters, height50 meters AII architectural works
Furnishings ofthe buildings
AII Mechanical Erection Works lora total of 42.000 !ons including
Boilers with all accessories Electrostatic precipitars
Turbine And Generator sets with all accessories Rotating machines
Fabricating Equipments
Coal , Ash and Lime Handling Systems Storage Tanks
WaterTreatmentPlants Handling Equipments FOSystems
LP, MP, HP lndoor and Outdoor Piping Fire Fighting and Extinguishing System
Gas Production plants, compressed air plants, auxiliary boiler packages, workshop and laboratories equipments
and other miscellaneous equipments. Steel Structure
HVAC
Refractories
Heat and sound lnsulation Cladding
Painting
AII Electrical Works including
Complete MW/LWSwitchgear System 21 pieces MW/LWTransformers
86.000 meters Cable Tray
700.000 meters Cabling
All lnstrumentation and Control Works Pre-Commissioning
Participating in commissioning and start-up

TEKNOTES ENERGY PRODUCTION PLANTS
320 MW Çan fluidized bed thermal plant
2*330 MW Maritza Thermal Power Plant
5*120 MW Rabigh Thermal Power Plant
210 MW Orhaneli Thermal Power Plant Flue Gas Desulphurization Plant
2*150 MW Catalagzi Thermal Power Plant
2*160 MW Cayirhan Thermal Power Plant
2*150 MW Kangal Thermal Power Plant
REFINERY AND PETROCHEMICAL PLANT
Kişladağ Gold Mine
Karabuk Air Seperation Plant Construction And Installation
Sinter II. Plant turnkey Const&Relocation Works Of Isdemir
Erdemir Gas Holder Tank Fabrication And Installation
Erdemir Gas Holder Tank Fabrication And Installation
Sivas Iron And Steel Factory
Iskenderun Iron&Steel Factory Blast Furnace Dedusting System
NATURAL GAS & OIL PIPELINES AND TANK FARMS
WATER TREATMENT PLANTS/WASTE WATER TREATMENT PLANTS
Ajjman Waste Water Treatment Plant And Pipelines
Chlef Waste Water Treatment Plant- Algeria
Rigga Waste Water Treatment Plant
Turkmenebad Water Treatment Plant
Sana'a Sewage Project
AIRPORT PROJECTS
Ataturk Airport International Terminal Baggage Handling System
Bodrum -Milas Airport New International Terminal Building Construction
MASS HOUSING PROJECTS-SHOPPING MALLS-TRADE CENTERS