CATALAGZI THERMAL POWER PLANT

2 x 150 MW ZONGULDAK / TURKEY

catalagzı-termik-santraliBoiler erection
High/low pressure proses piping fabrication and installation
Off-site piping fabrication and installation
Steel structure fabrication and installation
Electrofilters and dust precipitators fabrication and installation
Civil works
Rotary equipment erection
Electrical works and instrumentation
Equipment installation
Fabrications and installations in the machine hail
Fabrication, supply and installation of mud scrappers tor raw water intake pools

 

 

 

 

 

CATALAGZI THERMAL POWER PLANT SLUDGE DEWATERING AND COAL MIXING-WASHERY PLANT WITH LONG DISTANCE BELT CONVEYOR

363560 m, 400 tons/h CATALAGZI/ ZONGULDAK / TURKEY

catalagzı-komur-yıkamaLength 3560 m
3560 m, 400 tons/hour
Steel structure fabrication and installation
Rotary equipment erection
lnstrumentation
Medium-Tensile and Low-Tensile (MV/LV)electrical installation works
Equipment erection
Commissioning

 

catalgazi-termik-komur-hat

Read 11158 times

Media

No video? Get the DivX browser plug-in for Windows or Mac

TEKNOTES Tanıtım Videosu

Referance Map